Notice of Street Milling & Resurfacing Work

The City of Takoma Park will be resurfacing the streets noted on the table below beginning on Wednesday, August 27, 2014. The City’s contractor will be milling the street in preparation for paving. Paving is expected to take place after Labor Day starting on Tuesday, September 2, 2014.

Street

From

To

Milling

Paving

Mississippi Ave Hilltop Piney Branch 8-27, 8-28 9-02, 9-03
Sherman Ave Maple Hancock to Carroll Ave 8-28 , 8-29 9-04
Lee Ave Hancock Ave Maple Ave 8-28 , 8-29 9-04
Poplar Ave Elm Ave at Spring Park 6729 Poplar Ave 8-29 9-05
Columbia Ave Pine Hickory Ave 9-02 9-08
Elm Ave Poplar Woodland 9-03 9-09
Elm Ave Prince Georges Ave Ethan Allen (MD 410) 9-03 9-08
Glengary Ave Sligo Creek Pkwy Heather Alley    

The contractor will work from 7:00 am to 5:00 pm, Monday through Friday. Rain and other inclement conditions may delay the scheduled work.

The contractor will post no parking signs on the streets a day before starting the work. Milling will be done prior to paving and it might take either one (1) or  two (2) day depending on the length of the street. Paving operation will begin after milling, we anticipate a maximum 2 days period for each paving. During work hours, parking will not be permitted and access to the street will be restricted. Limited access may be available during milling operation. However, during paving through traffic will not be permitted for the duration of the operation.

We appreciate your cooperation and patience for any inconveniences you may experience during street resurfacing.