• No results found for this search.
CLOSE SEARCH

New Ave Bikeway

About the New Ave Bikeway

The goal of this project is to creatively redesign the underutilized service lanes on the southbound side on New Hampshire Avenue as a two-directional bikeway, while still providing vehicular access to properties.

The New Ave Bikeway is currently supported by a Maryland Bikeways grant, to develop design documents. It will provide design and consideration of pavement markings, signage, curb and sidewalk adjustments, vertical barriers between cyclists and vehicular traffic, and possible elimination of some curbside parking in the service lane.

This project builds on the 2012 New Ave Feasibility Study, the 2016 MWCOG grant for preliminary design, and the 2016 Bikeshare expansion into Ward 6. The outcome of the project is final engineering drawings that the City can use to apply for further funding to complete the Bikeway’s eventual construction. The City, in conjunction with MWCOG, selected a project consultant, Rummel, Klepper, and Kahl (RK&K) for the design work.

Current Project Status

FY22 Kim Lamphier Bikeways Network Program (MD-DOT) – Section B
In September, 2021 the City was awarded $254,000 in  funding to complete final designs and construction documents for Section B. The total project cost for this section is $318,000. Work on this portion of the project has not yet begun.

FY21 Maryland Bikeways Grant – Section A
In October 2020, the City was awarded $473,173.36 in MD Bikeways funding to complete final designs and construction documents for Section A. The total project cost for this section is $591,466.70. The grant agreement with the Maryland Department of Transportation was executed  in December 2020.

Montgomery Planning Board review: The New Avenue Bikeway, Section A, Mandatory Referral  (MR2021007)

FY20 Maryland Bikeways Grant – Section B
In September 2019, the City was awarded a MD Bikeways Grant of $235,000 to develop 60% designs for an additional portion of the Bikeway from Auburn Avenue to Poplar Avenue (Section B). The total project cost is $293,750. The grant agreement with the Maryland Department of Transportation was executed in December 2019.

For Section B, 30% designs have been completed. An agency stakeholder meeting was held in December 2020. A public meeting for resident input was held on February 18, 2021. Links to slides and color roll are posted in the right column under Preliminary Designs (30% Design) for Section B – Auburn Avenue to Poplar Avenue.

Montgomery Planning Board review: The New Avenue Bikeway, Section B, Mandatory Referral, October 28, 2021. (MR2021024)

FY18 MD Bikeways Grant – Section A
The New Ave Bikeway Project was awarded a Maryland Bikeways grant of $240,000 in November 2017 to continue design work for the project. The FY18 grant funds develop semi-final designs for a portion of the Bikeway from Auburn Avenue to Holton Lane (Section A). The total project cost for this section is $300,000.

A grant agreement with the Maryland Department of Transportation was executed in July 2018. City Council passed an ordinance to execute a contract for design and engineering services for the bikeway on September 5, 2018.

The City received a project extension in order to finalize designs for the M-NCPPC owned portion of the bikeway.

The 60% design was presented to City Council on September 16, 2020 (presentation slides). Montgomery Planning Board Mandatory Referral  (MR2021007) hearing was held February 18, 2021.

Project Lead & Contact Info

Alexander Freedman
Planner
Email: AlexanderF@takomaparkmd.gov

Southbound New Hampshire Avenue side service lane, looking north from Glenside Drive.
Southbound New Hampshire Avenue side service lane, looking north from Glenside Drive.

Quicklinks

New Ave Bikeway Details

New Ave Bikeway Project Area Map

Project Info & Timeline

Budget & Funding Sources:

Source of Grant Funds Award DATE
 ProjectGrant FundsCity FundsTotal
Maryland Bikeways2021Section B: Final Design Plans$254,000$64,000$318,000
Maryland Bikeways2020Section A: Final Design Plans$473,000$118,000$591,000
Maryland Bikeways2019Section B: Semi-Final Design Plans$235,000$58,750$293,750
Maryland Bikeways2018Section A: Semi-Final Design Plans$240,000$60,000$300,000
Metropolitan Washington Council of Governments2016Section A: Preliminary Design Plans$60,000$0$60,000
Metropolitan Washington Council of Governments2013Multi-Way Boulevard Feasibility Study$50,000$0$50,000
TOTAL$1,312,000$300,750$1,612,750
Preliminary and Semi-Final  Designs for Section B – Auburn Avenue to Poplar Avenue

The City was awarded a MD-Bikeways Grant for 30% designs,  completed in Fall/Winter 2020. A public meeting to review these designs in detail was held February 18, 2021.

Semi-Final Designs (Semi-Final Design) for Section A

The City was awarded a MD-Bikeways Grant for 60% designs, completed in late May 2020. These plans build on comments received on 30% plans above. Plans can be viewed at the links below.

Concept/Preliminary Design Plans for Section A – Holton Lane to Auburn Avenue

The City was awarded a Metropolitan Washington Council of Governments grant for preliminary design of the New Ave Bikeways Section A project. The first phase (Section A) of design of the New Ave Bikeway Project was completed in June 2017.

Project Timeline

  • Fall 2023
    Completion of 100% Design for Section B
  • Spring 2022
    Completion of 100% Design for Section A
  • Fall 2021
    Completion of 60% Design for Section B
  • Fall 2021
    Planning Board Mandatory Referral review on October 28, 2021 for Section B
  • Summer 2021
    Submission of Mandatory Referral Documents to M-NCPPC for Section B
  • February 2021
    Awarded MD Bikeways Grant 100% Design for Section A
  • February 2021
    Mandatory Referral Hearing for 60% Designs Section A
  • February  2021
    Community Meeting for 30% Designs for Section B
  • Winter 2020
    Completion of 30% Design for Section B
  • Fall 2020
    Completion of 60% Design for Section A
  • Summer 2020
    Community Outreach and Council Presentation for Section A
  • June 2020
    Initiation of Preliminary Design for Section B
  • September 2019
    Awarded MD Bikeways Grant 60% Design for Section B
  • Fall 2018 to Present
    Design Work and Agency Stakeholder Meetings (Ongoing)
  • October 2019
    Six Month Extension Granted by MD Bikeways
  • September 2018
    Council Approves Ordinance to Execute Contract for Design Services with RK&K
  • July 2018
    Grant Agreement Executed 
  • November 2017
    Awarded MD Bikeways Grant for 60% Design for Section A
  • June 2017
    30% Designs Completed
  • May 2017
    RK&K presented 30% Designs to Council for Section A
  • March 2017
    Community Meeting for 30% Design for Section A
  • February 16, 2017
    Stakeholders Meeting
  • July 2016
    MWCOG Technical Assistance Grant Awarded for 30% Design for Section A

Planning and Community Development Sections